Friday 15 June 2018

Town Centre saga part 2


TOWN CENTRE
As is normal with very large developments independent consultants are asked to check the developer’s figures. Having looked at these heavily redacted reports I have found some interesting information.

The Mall has 69 units in 24,155 sqm and was built in 1988 on a 250 year lease. The plan is to increase the Mall by adding 94,390 sqm of retail and leisure - nearly a 400% increase.

The four tower blocks will range from 12 to 29 storeys creating up to 500 flats. The Viability Assessment (VA) was carried out on an assumption of 471, but 600 units are being considered. The cost is expected to be in the region of £135m. Curiously blocks B and C will have 261 and 168 flats but D and E only 27 and 15. This means the VA has different information to the Planning Application which clearly states the blocks will be 12 to 29 storeys.

Apparently each block will have a lift for 13 people and a separate one for the fire lift and will cost in the region of £0.5m.

The substructure plan to allow the tower blocks to be built will be a platform built over the tube lines needing significant piles to support the platform. The consultants reckon the costs have been under estimated, which is not surprising as this would be a very skilled job and I doubt the detailed planning for this has yet been done.  They comment about the cost that “ there is a risk it may be insufficient subject to confirmation of substructure design. A detailed design risk assessment is still to be finalised.” They did not have sufficient information to accurately check the pricing.

C&R have allowed 14 months to prepare the site for the development which will mean the children’s playground and Big Screen will be removed and a walkway tunnel built to protect the existing entrance to the Mall, much like the “tunnel” currently over the entrance to Liverpool Station.

The actual construction work will take 52 months so even if they started now it would not be finished until 2024 at the earliest. They have also allowed 4.5 years to sell all the flats!

Clearly we will have plenty of questions if and when they submit their application for full planning permission for the tower blocks.



No comments:

Post a Comment

All comments welcome - but please be polite!